Material Requirements Planning
MRP determines:
which material is required,
in which quantity
What time
…then creates work order proposals
MPS usually runs for the first layer of products
MRP runs for every level in the BOM (depth can
be specified)
Runs frequently on individual materials
(less often
global –
system workload)
Create new / modify existing plans
Create purchase requests
Delivery schedules for externally procured items